Fixing a 150 Year Old Clay Pipe
Location:
|
City of London, London's Minories
|
Client:
|
AXA
|
Service:
|
Property Maintenance, Special Project
|
Sector:
|
Office
|
Value:
|
£250,000
|
Notes:
|
Finished On Time and On Budget
|
Project Gallery
How do you solve the problem of a broken sewer pipe that is 10m below ground level
underneath the basement of a multi-story office block in the City of London when
you cannot dig up the street, cannot make a noise during office hours, and cannot
place skips for rubbish removal because of the fears of bombs?
This was the problem that faced the owners of the building in London's Minories
a few months ago. After calling in the drain clearance experts, it was established
by the use of cameras that a l50-year old clay pipe had fractured and collapsed
and so a call Was made to RDF Group to see if they could solve the problem.
Having had a look at this particular situation, we carried out a desktop survey
in order to ascertain what problems we might encounter. What we discovered was that
the pipe that had fractured and collapsed ran down at an angle of 45° to a depth
of some 10m below road level and appeared to be very close to the Circle Line of
the London Underground. In order to get access to the collapsed area. we would have
to sink a shaft but you cannot do this at 45° and so we bad to find an alternative
solution. In the meantime, the basement was gradually filling with sewage from the
fractured pipe!
Broken Sewer Pipe
The first task was to solve the problem of the sewage. As has already been explained.
because of the location of the building within the City of London, no work could
be carried out from the street and it was not permitted to create any noise during
normal office working hours, except for one hour during the afternoon and then after
7pm. With this in mind, an enormous sewage tank was created in part of the basement
of the building and this was then pumped out every 24 hours, in order to keep the
office block working.
Sinking A Shaft
Tbe next stage was to estimate just where the exact collapsed area of pipe was located
in order to sink 3 vertical shaft down to it. Heavy gauge (8mm thick) steel piles
were then driven hydraulically down, using silent hydraulic jacks, to the I Om level.
working from the basement,which was itself about 4m deep. This had to be done hy
working through the night, having first cut through the bearing foundation pad of
the multi-storey building, which had several hundred ronnes of pressure bearing
down upon it. As the piles were driven down, the enclosed soil and debris was removed
during the day, directly into waiting lorries, to be ta ken away. Once the 10m level
had been reached, a hole was cut in the side of I the shaft that had been created
and a reinforced steel tunnel formed, allowing access to the fractured area of pipe.
The Fractured and Collapsed Pipe
Robert Webb explains: "What we found was that the pipe adjacent to the collapsed
length was embedded in the concrete lining of the Underground. We were warned by
Transport for London (Ttl) that if we found that the fracture went under the railway
tunnel lining, then we would have to install a laserguided monitoring system on
the walls of the working tunnel in order to detect any movement and, furthermore,
take out insurance to the value of £150 million!" The fracture was in a 12-inch
diameter clay pipe that had been installed at least 150 years earlier and was shown
clearly on a drawing that was obtained from Ttl's archives showing the original
'Metropolitan Railway plan of the Aldgate to Tower Hill Extension with a Stoneware
Drain Pipe on West Side of Minories'. The team carried out a camera survey of the
pipe where it went into the concrete lining and discovered several more cracks.
Making the Repair
It was decided to line the cracked section of the clay pipe and so a fibreglass
'balloon' was inserted into the pipe and inflated. Once this had cured, a cutting
tool was sent down to the far end to remove the end of the balloon, leaving a sound
lining. A new 12-inch diameter cast iron pipe was then connected to the original
clay pipe and a deep manhole created. The steel shaft was then filled with concrete
that was aerated to ensure that there were no voids that might lead to slippage.The
building's sewer pipes were then diverted into the new manhole and the floor replaced.
Safe Working Practices
"Because of the conditions in which we were working, it was essential that all of
our operatives were fully trained in working at depth and in working in confined
spaces. All of our team are trained in these areas and are equipped and trained
to use breathing equipment," explained Robert. "We installed a dedicated fresh air
supply and set up constant air quality monitoring equipment with alarms sounding
in case of a gas build-up or low oxygen levels. "The project took about three months,
although we were only actually on site for about two-thirds of this. It was an interesting
encounter for our whole team, even though we are well-experienced in working on
this type of project. We also had some interesting comments: Steve Lane,1\Contracts
Manager: "This is certainly one of the most unusual projects 1have been involved
with. The whole tunnel would vibrate as the trains rattled down the tunnel just
a few feet away on the other side of the wall."
The Transport for London Inspector: "I went to the site again yesterday and I was
very pleased with my observations, the shaft and the tunnel have been very well
propped and the fall-arrest system not only in place but it was being used. The
site was kept clean and well managed with good hygiene facilities in place. When
we see a site managed like this we have confidence that our infrastructure is being
protected. Please convey my thanks to the site crew." Robert concluded, "I would
say that this is probably the most technically challenging job thor we have tackled.
However, over the last 21 years we have done many projects and are probably
one of a very small number of companies that could have done this job. All our projects
are engineered in-house using the latest AutoCad and 3D-modelling, but, above all,
I like to thiuk that we still retain my father's values of quality of work, attention
to detail and customer service."